Footbridge - Avrieux (France)

Contracting authority:

Town Hall of Avrieux

 

Challenges:

Replacing of the old bridge over the Creek of the Fond on the commune of Avrieux at 2,200m altitude, in  the Maurienn territorial pastoral plan..

 

Missions:

Removing the old bridge.

Supply and installation of the new one.

 

Items for public access:

  • Rigid bridge : L16m / l 1.5m

 

Completion date:

  • Removal: 2 days to 4 technicians

Assembly 3 days to 3 technicians access technicians (without concrete)